It is usually the second question in an enquiry, arriving somewhere just after price. There is a date in mind: a trade show, a rebrand going live, a new season starting, a lease on a new unit. What the person on the phone needs to know is whether a website can be ready by then.
For a standard business website the answer is three to six weeks from the point where we agree to go ahead. That is a wide range for something that sounds as though it ought to be a fixed number, so the rest of this sets out what happens in each stage, how long each one actually takes, and which parts of the schedule sit with me and which sit with you. By the end you should be able to look at your own circumstances and work out roughly where in that range you would land.
Why it is a range and not a number
A website is not one job. It is a design job, a writing job, a technical build and a testing exercise, and they do not run in a tidy line with a clean handover between each one. Some overlap. One or two cannot begin until something arrives from your side of the table.
The length of a project is therefore set less by the number of pages than by how many decisions have to be made and how quickly they get made. A ten page site for an owner who knows exactly what the business does, and who replies the same afternoon, will finish before a five page site where three directors need to agree on a paragraph.
I build in stages and you watch the site grow rather than waiting for a reveal at the end. That matters for the timeline as much as for the nerves, because anything that needs changing surfaces while it is still a small change.
Stage one: the discovery call
This is a conversation, usually around an hour, and it is where I find out what the site has to do. Not what it should look like, which comes later, but what a good month looks like for the business, who you want to hear from, what the current site fails to do, and what would count as the project having worked.
Booking the call is normally the only delay here, and that depends on both our diaries. The call itself is a single session. Where a project is more involved, an online shop or something with an unusual process behind it, there may be a second conversation to go through the detail.
Allow a few days to a week for this stage, most of which is scheduling rather than work.
Stage two: the written scope
After the call I write the project up: what is being built, what is included, what is not, and a fixed price. This is the document everything else is measured against, and it exists so that neither of us is relying on memory in week five.
Writing it takes me a day or two. What varies is how long it then sits with you. Some people read it and confirm the same evening. Others need to take it to a partner or a board, and that is entirely reasonable, but it is time on the clock. If there is a hard launch date, this is the first place where a week can quietly disappear.
Once the scope is agreed and signed off, the project has a start date.
Stage three: the home page, designed for real
This is the stage that surprises people, and it is the one I would defend hardest. Rather than sending a flat picture of a design, I design and build the home page for real in the browser, so you can open it on your laptop and your phone and click through it.
You are then judging the actual thing rather than an impression of it. Fonts behave as they will behave. The menu opens. The buttons do what buttons do. It is a far better basis for a decision than a static image, and it prevents the common and expensive discovery that a design which looked splendid at A4 does not survive contact with a real phone.
Expect one to two weeks here, including a round or two of changes. This is the longest single creative stage and it is worth taking properly, because once the home page is signed off the rest of the site follows in the same visual language and moves considerably faster.
Stage four: the build
With the design settled, the inner pages get built: services, about, contact, the blog, the legal pages, and whatever else the scope listed. Forms are wired up and tested. The site is made to work properly on phones and tablets rather than merely fitting on them. Anything technical the project needs, a booking form, a shop, an integration with software you already use, is built and tested in this stage.
For a straightforward business site this takes one to three weeks. An online shop takes longer, because a shop is a set of processes rather than a set of pages, and products, postage rules, tax settings and payments all have to be right before anyone can buy anything. My WordPress website development work covers both, and the scope will have told you which shape your project is.
This is also the stage that depends most heavily on your content. More on that shortly.
Stage five: launch and support
Launch day itself is a few hours of work, done at a quiet time for your business. The site goes live, the old one comes down, redirects are put in place so that existing search results and old links still land somewhere sensible, and analytics start recording.
Then there is a settling-in period of a week or two where small things get noticed and put right. A wrong phone number, a photograph that should have been the other one, a page that turns out to need an extra paragraph. This is normal and I plan for it.
The two things that stretch projects
Every project that has run long in sixteen years has run long for one of two reasons, and neither of them is the building.
The first is content arriving late. Text and photographs are the raw material of the site, and a page cannot be finished around content that is not there. Writing about your own business is also harder than it looks, which is why it slips down the list behind the actual running of the business. A build can be paused for a month waiting on the About page, and the fortnight of technical work left to do does not shrink to compensate.
The second is slow feedback. When the home page goes over for review, the project stops until it comes back. Three days to gather comments from a couple of colleagues is perfectly fine and I plan for it. Three weeks because everyone is busy is three weeks added to the end, and it is added twice if it happens at the design stage and again at the review stage.
Neither of these is a criticism. Businesses are busy and websites are not usually anybody’s main job. They are simply the mechanics of how projects run, and knowing about them in advance is what lets you protect a launch date. If you can get your text and images together before the build starts, and nominate one person to collect feedback and send it in one go, you have already removed most of the risk to your schedule.
When four weeks is realistic
Four weeks happens, and it happens under specific conditions. The site is a standard business website of five to ten pages. The content already exists, either from the old site or written and ready in a document. Decisions rest with one person who can say yes without a committee. Feedback comes back within a day or two. There is nothing unusual to build behind the scenes.
That is a well prepared project rather than a rushed one, and it is more common than you might think among owner-managed businesses.
When it is twelve
Twelve weeks is also perfectly normal, and it is usually a bigger project rather than a troubled one. An online shop with a real catalogue. A site with dozens of pages, or several distinct audiences to serve. Photography or video that has to be commissioned and shot. Copy being written from scratch, by you or by a copywriter, alongside the build. A committee, a board or a franchise brand team in the approval chain.
It can also be twelve weeks because a four week project met a busy quarter. That is the version worth planning around, because it is the avoidable one.
If you have a fixed date, say so in the first conversation. It changes how I sequence the work and it tells me whether the date is realistic before either of us has committed to anything. You can start that conversation here, and I will give you a straight answer rather than an optimistic one.
Common questions
How long does a WordPress website take to build?
Three to six weeks is typical for a standard business website, measured from the point where the scope is agreed rather than from the first enquiry. Online shops and larger sites run longer, often ten to twelve weeks, mostly because there is more to set up behind the scenes rather than more pages to design.
Can you build a website in two weeks?
Sometimes, for a small site where the content is already written and the decisions rest with one person. It is not the normal shape of a project and it requires everything on your side to be ready before we start. If a hard deadline is driving it, tell me at the first call and I will give you a straight answer on whether it is achievable.
What do you actually need from me, and when?
Text and images for each page, your logo and brand files if you have them, and access to your domain and hosting. The most useful thing you can do is have the content ready before the build stage begins, because that is where the wait would otherwise happen. Beyond that, prompt answers when the home page goes over for review.
What happens if we miss the launch date?
We talk about it as soon as it looks likely rather than on the day. Usually the fix is to launch a smaller site on time and add the remaining pages afterwards, which is straightforward with WordPress and often the better outcome anyway. A live site that is missing a case studies page still works. A finished site that arrives after the trade show does not.